Project Type: Skyscrapers
New York Life Building
Project Location: New York, NY
Project Time Frame: 2004 - Present
Scope of Work: Developed a comprehensive Roof Management Program. Developed Specifications to restore all roofs to this 1928 landmark
Roofing Contractor: Multiple Contractors
Roof System: Siplast modified bitumen
Unique Benefit: Historical society challenges was handled. Plumbing issues with galvanized piping were interfaced
919 Third Avenue
Project Location: New York, NY
Project Time Frame: 1996 - Present
Scope of Work: Design & monitor application of new roof and runway
Roofing Contractor: Arrow Restoration
Roof System: Modified bitumen & concrete restoration
Unique Benefit: Restored a concrete runway used for the window washing rig
61 Broadway, Manhattan (AKA: American Express Building)
Project Location: New York, NY
Project Time Frame: 2001
Scope of Work: Design & monitor application of the new roof
Roofing Contractor: Jobin Contracting
Roof System: Modified bitumen
Unique Benefit: Roof deck is comprised of terracotta forms with cinder fill. This deck was later banned from use. Roof Solutions understood and adjusted the design saving six figures
Fred French Building
Project Location: New York, NY
Project Time Frame: 2001 - 2002
Scope of Work: Design & monitor application of new roof to this 1927 historical building
Roofing Contractor: Arrow Construction
Roof System: Siplast modified bitumen
Unique Benefit: Numerous set backs and historical society challenges